JEAces teamed with PTGcsc to provide CEI services on this $110M interchange project that extended I-295 over US-1 and constructed a new interchange linking I-95, I-295, and SR 9A. Construction elements included 1M CY of excavation, 1.5M CY of embankment, 181 drainage structures, over 5 miles of storm drain pipe as well as asphalt and concrete pavement. The 10 bridges on the project included three high level segmental box girder bridges, one 63-inch Florida U-Beam bridge carrying Greenland Road over I-95, two 54-inch Florida U-Beam bridges carrying SR 9A over I-95, two 72-inch Bulb-T beam bridges carrying SR 9A over US-1 and the FEC railroad, and two AASHTO Type III Beam bridges carrying I-295 over Julington Creek.
SERVICES: Bridge, Rehabilitation
CLIENT: Florida Department of Transportation
SERVICES: Landscaping
CLIENT: Florida Department of Transportation
SERVICES: Landscaping
CLIENT: Florida Department of Transportation
SERVICES: Other, Compliance Services
CLIENT: Florida Department of Transportation